Cemetery plan

Nebraska Muslim Cemetery

Key milestone dates:

Date of purchase of the land     : January 13th, 2023.

Date when burials will start at the cemetery : To Be Announced. (Estimated in May 2024).

Federal approval for non-profit status :       December 5th, 2023.

State approval for non-profit status : May 4th, 2023.

State approval for tax exempt status : March 29th, 2024.

Phase-1 completion date : Tentatively May or June 2024.

Start of burials : After Phase-1 completion that is May or June of 2024.

Phase-2 start date : In-Planning. Collecting donations for phase-2.

Cemetery approval received from the county  : April 8th, 2024.

Nebraska Muslim Cemetery project details.docx.pdf

Nebraska Muslim Cemetery (NeMC) plan.

Cemetery will be built in two phases. Refer to the plan for more details.

For Pictures of the Cemetery, click here.